Maybe our company is an odd one out but I'm pretty sure that number is more like 20-30%....

Out of a team of 10, 2 of us do about 50% of the work. 3 do about 30%, and the remaining five do about 20%... With probably two to three of them doing effectively nothing most of the time.

In our team isn't abnormal.

  • source
  • hideshow 2 child comments
  • [–] [S] 1 point 2 years ago

    I will say I worked one job where we had to submit network changes which was supposed to be checked by 5 different network engineers and then implemented.

    Those 5 people would take a couple months just to fuck up my requests every gd time.